Question
A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?
Options
- ABegin transitioning program resources, and update the resource and program management plans
- Binitiate knowledge transfer with the receiving organization, and establish the program integration
- CUpdate the financial stakeholder, and contract management plans and archive them in the
- DObtain sponsoring organization approval to begin closeout procedures to transition benefits
Unlock RCDDV15 to see the answer
You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.