What would prevent a program manager from completing program closure once a program has been completed?
The correct answer is D. Failure to obtain program steering committee approval. See the full explanation below for the reasoning.
Program Governance
Question
What would prevent a program manager from completing program closure once a program has been completed?
Options
- AFailure to update the financial management plan
- BFailure to update the benefits register
- CIncomplete realization of all program benefits
- DFailure to obtain program steering committee approval
How the community answered
(22 responses)- A5% (1)
- B5% (1)
- C9% (2)
- D82% (18)
Topics
#program closure#steering committee approval#governance approval#program completion prerequisites