What would prevent a program manager from completing program closure once a program has been completed?

The correct answer is D. Failure to obtain program steering committee approval. See the full explanation below for the reasoning.

Program Governance

Question

What would prevent a program manager from completing program closure once a program has been completed?

Options

  • AFailure to update the financial management plan
  • BFailure to update the benefits register
  • CIncomplete realization of all program benefits
  • DFailure to obtain program steering committee approval

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    9% (2)
  • D
    82% (18)