Question
An organization requests that a junior project manager, with no previous experience or training in the industry take over a complex program component. The program component involves senior subject matter experts and has dependencies with other large projects to deliver key benefits to the organization. How should the junior project manager respond to this request?
Options
- AAccept the assignment, identify the skill gaps and request training
- BReject the assignment, because of the ethical requirement not to accept work for which the
- CAccept the assignment as a challenge and an opportunity to acquire new skills and seek advice
- DReject the assignment because of fear of failure and resulting negative career impact