To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is…

Sign in or unlock RCDDV15 to reveal the answer and full explanation for question #89. The question stem and answer options stay visible for context.

Program Governance

Question

To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized. What should the program manager do?

Options

  • ADocument the concerns that program goals may be affected and present at the next program
  • BAdvise the program sponsor that the program will continue and follow the program management
  • CWork with the project managers of the affected components to implement fast tracking and
  • DEvaluate critical success factors and key performance indicators (KPIs) to monitor benefits

Unlock RCDDV15 to see the answer

You've previewed enough free RCDDV15 questions. Unlock RCDDV15 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#program acceleration#sponsor management#program governance#benefits delivery risk