To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is…
The correct answer is B. Advise the program sponsor that the program will continue and follow the program management. See the full explanation below for the reasoning.
Program Governance
Question
To create market advantage, a program sponsor requests accelerating the implementation of a new manufacturing process that is based on a recently improved system component. The program manager is concerned that the delivery of some program goals could be jeopardized. What should the program manager do?
Options
- ADocument the concerns that program goals may be affected and present at the next program
- BAdvise the program sponsor that the program will continue and follow the program management
- CWork with the project managers of the affected components to implement fast tracking and
- DEvaluate critical success factors and key performance indicators (KPIs) to monitor benefits
How the community answered
(34 responses)- A3% (1)
- B76% (26)
- C15% (5)
- D6% (2)
Topics
#program acceleration#sponsor management#program governance#benefits delivery risk