Question
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase. Tracking and reporting of actual benefits realized is one part of the review. What is the other part of the review"?
Options
- ATracking and reporting on benefits management plan
- BIdentifying factors Influencing delivery of benefits
- CDemonstrating that other stage gate requirements have been met
- DGathering additional stakeholders' requirements