Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while…
The correct answer is A. Review the issue with the program management office (PMO) to determine which template to use. See the full explanation below for the reasoning.
Program Governance
Question
Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another. How should the program manager decide which template is appropriate?
Options
- AReview the issue with the program management office (PMO) to determine which template to use
- BReview the issue with the project managers and come to mutual agreement on which template to
- CMeet with the program governance board to select an appropriate template
- DAllow the component project managers to use their preferred templates
How the community answered
(32 responses)- A75% (24)
- B9% (3)
- C3% (1)
- D13% (4)
Topics
#PMO authority#template standardization#communications governance#program standards