nerdexam
BICSI

RCDDV15 · Question #102

Stakeholders ask the program manager to assess reasons for the project's delay and provide a report also, the program manager must identify steps to be taken to ensure the program will finish on…

The correct answer is D. Communications management plan. See the full explanation below for the reasoning.

Program Communications Management

Question

Stakeholders ask the program manager to assess reasons for the project's delay and provide a report also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget. The program manager distributes information in accordance with which of the following?

Options

  • AStakeholder engagement plan
  • BProgram governance charter
  • CSchedule management plan
  • DCommunications management plan

How the community answered

(16 responses)
  • A
    19% (3)
  • B
    6% (1)
  • C
    6% (1)
  • D
    69% (11)

Topics

#communications management plan#information distribution#stakeholder reporting#schedule management

Community Discussion

No community discussion yet for this question.

Full RCDDV15 Practice