Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

The correct answer is A. Program performance report. See the full explanation below for the reasoning.

Program Communications Management

Question

Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?

Options

  • AProgram performance report
  • BCommunications management plan
  • CCommunications log updates
  • DInformation gathering and retrieval system

How the community answered

(44 responses)
  • A
    70% (31)
  • B
    5% (2)
  • C
    9% (4)
  • D
    16% (7)

Topics

#program performance report#status reporting#cost information#risk reporting