The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program…

The correct answer is C. Resource interdependency management. See the full explanation below for the reasoning.

Program Resource Management

Question

The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B. This is an example of which of the following?

Options

  • AProgram resource management planning
  • BProgram risk mitigation
  • CResource interdependency management
  • DProject resource planning

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    11% (6)
  • C
    80% (44)
  • D
    5% (3)

Topics

#resource interdependency#over-allocation#resource management#component projects