A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project. What should the…

The correct answer is C. Review the skill requirements of the project. See the full explanation below for the reasoning.

Program Resource Management

Question

A project is assigned to a qualified project manager by the program manager. The client rejects the project manager due to a lack of proper qualifications to manage such a project. What should the program manager do next?

Options

  • AReassess the project manager's credentials
  • BAssign a different project manager
  • CReview the skill requirements of the project.
  • DApply the competence assessment techniques to resolve the issue

How the community answered

(39 responses)
  • A
    15% (6)
  • B
    3% (1)
  • C
    74% (29)
  • D
    8% (3)

Topics

#resource management#project manager competency#client relations#skill requirements