RCDDV15 · Question #206

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive…

The correct answer is A. Program definition. See the full explanation below for the reasoning.

Program Life Cycle Management

Question

An initiative involves the development of new technology and leverages existing technologies. It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place. In what phase is the risk management plan created?

Options

  • AProgram definition
  • BProgram execution management
  • CProgram delivery
  • DProgram risk management planning

How the community answered

(45 responses)
  • A
    71% (32)
  • B
    4% (2)
  • C
    9% (4)
  • D
    16% (7)

Topics

#risk management plan#program definition phase#program lifecycle#governance board

Community Discussion

No community discussion yet for this question.