RCDDV15 · Question #113

A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?

The correct answer is C. Prioritize the resource to optimize their use across both projects A and B. See the full explanation below for the reasoning.

Program Resource Management

Question

A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?

Options

  • AAssign project A's resource to project B
  • BReassign the resource to project B after protect A ends
  • CPrioritize the resource to optimize their use across both projects A and B
  • DMitigate risk by leveraging other resources in project A

How the community answered

(39 responses)
  • A
    15% (6)
  • B
    3% (1)
  • C
    74% (29)
  • D
    8% (3)

Topics

#resource optimization#cross-project allocation#resource utilization#resource prioritization