A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before…

The correct answer is A. Program governance plan. See the full explanation below for the reasoning.

Program Governance

Question

A large program consists of several component projects and six project managers. The program governance board requests that all components within the program undergo user acceptance testing before being released to the production environment. Where should the program manager document this?

Options

  • AProgram governance plan
  • BProgram requirements
  • CComponent test plan and test cases
  • DProgram quality management plan

How the community answered

(49 responses)
  • A
    84% (41)
  • B
    2% (1)
  • C
    4% (2)
  • D
    10% (5)

Topics

#program governance plan#user acceptance testing#quality requirements#governance documentation