Scrum
PSD · Question #66
The role of the scrum master during the daily scrum is:
The correct answer is E. Make sure all three questions of the daily scrum are answered. The scrum master doesn't need to be present during the daily scrum. Neither does the daily scrum need to consist of three questions, which is a commonly chosen format though.
Applying Scrum
Question
The role of the scrum master during the daily scrum is:
Options
- AManage the meeting
- BAll of these
- CLead the discussion
- DEnsure that the meeting takes place and that its timebox won't be exceeded
- EMake sure all three questions of the daily scrum are answered
How the community answered
(60 responses)- A2% (1)
- B5% (3)
- C3% (2)
- D2% (1)
- E88% (53)
Explanation
The scrum master doesn't need to be present during the daily scrum. Neither does the daily scrum need to consist of three questions, which is a commonly chosen format though.
Topics
#scrum master#daily scrum#facilitation#timebox