Who is responsible for a sprint backlog item that contains several database tasks?

The correct answer is A. The developers. Developers are responsible for conducting the work on the sprint backlog

Applying Scrum

Question

Who is responsible for a sprint backlog item that contains several database tasks?

Options

  • AThe developers
  • BProduct owner
  • CThe company's database specialist
  • DScrum master

How the community answered

(43 responses)
  • A
    91% (39)
  • B
    2% (1)
  • C
    5% (2)
  • D
    2% (1)

Explanation

Developers are responsible for conducting the work on the sprint backlog

Topics

#Sprint Backlog ownership#Developer responsibility#Scrum team accountability