Who is responsible for a sprint backlog item that contains several database tasks?
The correct answer is A. The developers. Developers are responsible for conducting the work on the sprint backlog
Applying Scrum
Question
Who is responsible for a sprint backlog item that contains several database tasks?
Options
- AThe developers
- BProduct owner
- CThe company's database specialist
- DScrum master
How the community answered
(43 responses)- A91% (39)
- B2% (1)
- C5% (2)
- D2% (1)
Explanation
Developers are responsible for conducting the work on the sprint backlog
Topics
#Sprint Backlog ownership#Developer responsibility#Scrum team accountability