PSD · Question #76
Upon what type of process control is scrum based?
The correct answer is C. Empirical. If you are not sure, please review the Scrum theory section in the scrum guide
Applying Scrum
Question
Upon what type of process control is scrum based?
Options
- ADeductive
- BHybrid
- CEmpirical
- DTechnical
How the community answered
(34 responses)- B3% (1)
- C91% (31)
- D6% (2)
Explanation
If you are not sure, please review the Scrum theory section in the scrum guide
Topics
#empirical process control#scrum foundations#process theory
Community Discussion
No community discussion yet for this question.