Scrum
PSD · Question #83
PSD Question #83: Real Exam Question with Answer & Explanation
Sign in or unlock PSD to reveal the answer and full explanation for question #83. The question stem and answer options stay visible for context.
Question
How is the management external to the Scrum team involved in the daily scrum?
Options
- AThe product owner speaks on their behalf
- BThe developers self-manage and they are the only management required at the daily scrum
- CThe scrum master speaks on their behalf
- DThe scrum master lets them know whether they need to be preset
Unlock PSD to see the answer