Scrum
PSD · Question #82
Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.
The correct answer is A. True. The scrum guide says: "The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."
Applying Scrum
Question
Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.
Options
- ATrue
- BFalse
How the community answered
(19 responses)- A95% (18)
- B5% (1)
Explanation
The scrum guide says: "The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."
Topics
#Sprint retrospective#Sprint backlog#Continuous improvement