Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.

The correct answer is A. True. The scrum guide says: "The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."

Applying Scrum

Question

Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.

Options

  • ATrue
  • BFalse

How the community answered

(19 responses)
  • A
    95% (18)
  • B
    5% (1)

Explanation

The scrum guide says: "The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."