Scrum
PSD · Question #14
Which of the following are required by Scrum? (choose all that apply)
The correct answer is G. None of the above.. Scrum does not prescribe specific tools or techniques like burn-down charts or unit tests. These are optional practices that teams may adopt to meet their goals effectively.
Applying Scrum
Question
Which of the following are required by Scrum? (choose all that apply)
Options
- ARelease burn-up.
- BBurn-down chart.
- CUnit tests.
- DCritical path analysis.
- ERefactoring.
- FBuild automation.
- GNone of the above.
How the community answered
(20 responses)- D5% (1)
- F5% (1)
- G90% (18)
Explanation
Scrum does not prescribe specific tools or techniques like burn-down charts or unit tests. These are optional practices that teams may adopt to meet their goals effectively.
Topics
#Scrum requirements#optional practices#unit testing#build automation
Community Discussion
No community discussion yet for this question.