Scrum
PSD · Question #88
A scrum master is working with developers that are spread over different locations. They have a variety of meeting rooms and the daily scrum is a logistic struggle every day. What actions should the s
The correct answer is A. Allow the developers to self-manage and decide what to do their selves.. Self management is important. All the other options the scrum master takes a decision by himself, it is better if the solution comes from the development team.
Applying Scrum
Question
A scrum master is working with developers that are spread over different locations. They have a variety of meeting rooms and the daily scrum is a logistic struggle every day. What actions should the scrum master take?
Options
- AAllow the developers to self-manage and decide what to do their selves.
- BRaise it as an impediment and make sure that management solves it.
- CCreate a schedule and alternate who is responsible for the daily scrum logistics
- DDecide the best solution and arrange a meeting to inform the developers.
How the community answered
(31 responses)- A74% (23)
- B13% (4)
- C10% (3)
- D3% (1)
Explanation
Self management is important. All the other options the scrum master takes a decision by himself, it is better if the solution comes from the development team.
Topics
#Scrum master role#Self-management#Daily Scrum#Distributed teams