Scrum
PSD · Question #15
While developing a new feature, you find a bug delivered in a previous Increment. What should you do? (choose the best answer)
The correct answer is D. Talk to the Product Owner about what steps to take.. The Product Owner prioritizes the work in the Product Backlog, including bugs. Developers should collaborate with the Product Owner to decide how to address the bug without jeopardizing
Applying Scrum
Question
While developing a new feature, you find a bug delivered in a previous Increment. What should you do? (choose the best answer)
Options
- ASet aside the Sprint Goal until the bug is fixed.
- BRevise the tests so that the bug no longer appears on the bug report.
- CStub out the code that caused the bug so it no longer occurs.
- DTalk to the Product Owner about what steps to take.
How the community answered
(40 responses)- A3% (1)
- B10% (4)
- C5% (2)
- D83% (33)
Explanation
The Product Owner prioritizes the work in the Product Backlog, including bugs. Developers should collaborate with the Product Owner to decide how to address the bug without jeopardizing
Topics
#bug handling#Product Owner collaboration#Sprint execution#technical debt