Question
Which of the following is true about the Definition of Done? (choose the best two answers)
Options
- AIt defines a state when the entire Increment is releasable.
- BIt might be a subject of discussion during the Sprint Retrospective.
- CIt is synonymous with acceptance criteria.
- DIt is the sole responsibility of the Developers to define it.
- EIt can only be extended; nothing can be removed.