Which of the following is true about the Definition of Done? (choose the best two answers)
The correct answer is A. It defines a state when the entire Increment is releasable. B. It might be a subject of discussion during the Sprint Retrospective.. The Definition of Done ensures an Increment is releasable and provides transparency. It can be refined over time to enhance quality, and its application can be reviewed during Retrospectives.
Applying Scrum
Question
Which of the following is true about the Definition of Done? (choose the best two answers)
Options
- AIt defines a state when the entire Increment is releasable.
- BIt might be a subject of discussion during the Sprint Retrospective.
- CIt is synonymous with acceptance criteria.
- DIt is the sole responsibility of the Developers to define it.
- EIt can only be extended; nothing can be removed.
How the community answered
(49 responses)- A92% (45)
- C4% (2)
- D2% (1)
- E2% (1)
Explanation
The Definition of Done ensures an Increment is releasable and provides transparency. It can be refined over time to enhance quality, and its application can be reviewed during Retrospectives.