PSD · Question #89

PSD Question #89: Real Exam Question with Answer & Explanation

The correct answer is D. Scrum is like traditional project management, but then with project managers replaced by self-. Scrum is not a methodology, because it doesn't fill in the details, it's a framework. Next to that, it is not like traditional project management where time, cost and scope are fixed.

Question

Which are not true about scrum? Choose two.

Options

  • AScrum is a framework for developing and sustaining complex products.
  • BEach component of scrum serves a specific purpose and is essential to Scrum's success
  • CScrum is based on empirical process control
  • DScrum is like traditional project management, but then with project managers replaced by self-
  • EScrum is a methodology based on empirical process control.

Explanation

Scrum is not a methodology, because it doesn't fill in the details, it's a framework. Next to that, it is not like traditional project management where time, cost and scope are fixed.