Scrum
PSD · Question #89
PSD Question #89: Real Exam Question with Answer & Explanation
The correct answer is D. Scrum is like traditional project management, but then with project managers replaced by self-. Scrum is not a methodology, because it doesn't fill in the details, it's a framework. Next to that, it is not like traditional project management where time, cost and scope are fixed.
Question
Which are not true about scrum? Choose two.
Options
- AScrum is a framework for developing and sustaining complex products.
- BEach component of scrum serves a specific purpose and is essential to Scrum's success
- CScrum is based on empirical process control
- DScrum is like traditional project management, but then with project managers replaced by self-
- EScrum is a methodology based on empirical process control.
Explanation
Scrum is not a methodology, because it doesn't fill in the details, it's a framework. Next to that, it is not like traditional project management where time, cost and scope are fixed.