Scrum
PSD · Question #65
PSD Question #65: Real Exam Question with Answer & Explanation
The correct answer is A. typically 10 or fewer people. The scrum guide says: "The Scrum Team is small enough to remain nimble and large enough to complete significant work within a Sprint, typically 10 or fewer people. "
Question
What is the size of the scrum team?
Options
- Atypically 10 or fewer people
- Bthis differs every sprint
- Cat least 8 people
- D3 to 11
Explanation
The scrum guide says: "The Scrum Team is small enough to remain nimble and large enough to complete significant work within a Sprint, typically 10 or fewer people. "