Scrum
PSD · Question #64
PSD Question #64: Real Exam Question with Answer & Explanation
The correct answer is A. As needed, taking into account a short term reduction in productivity. Changing the team members is sometimes necessary, this will have an effect on productivity. So it should only be used when really necessary.
Question
The scrum team should change in members:
Options
- AAs needed, taking into account a short term reduction in productivity
- BEvery sprint to remain agile
- CNever, it will reduce the velocity
- DAs needed, but it should not affect the productivity
Explanation
Changing the team members is sometimes necessary, this will have an effect on productivity. So it should only be used when really necessary.