PSD · Question #63

What statement best describes the product backlog?

The correct answer is A. It is an emergent, ordered list of what is needed to improve the product. It is not fixed, it is a live artifact that will grow and change as more is learnt. The product owner orders it by value.

Developing Products

Question

What statement best describes the product backlog?

Options

  • AIt is an emergent, ordered list of what is needed to improve the product
  • BIt is the diary of the product owner
  • CIt is mainly meant as inspiration for the sprint planning
  • DIt is a list of all the requirements that will have to be added to the product

How the community answered

(28 responses)
  • A
    89% (25)
  • B
    4% (1)
  • D
    7% (2)

Explanation

It is not fixed, it is a live artifact that will grow and change as more is learnt. The product owner orders it by value.

Topics

#product backlog#backlog management#ordered list#emergent planning