What are three of the best ways to address non-functional requirements?
The correct answer is A. Handle them during a risk mitigation phase before development E. Specific expectations can be used as acceptance criteria to specific product backlog items F. Important, recurring non-functional requirements can be added to the definition of done. There is no hardening sprint, there are only regular sprints. If it's an ever recurring non-functional requirement, it can be added to the definition of done. If it's not it can be added (as a criteria) in the product backlog (item).
Question
What are three of the best ways to address non-functional requirements?
Options
- AHandle them during a risk mitigation phase before development
- BScrum is for functional, frontend development only
- CInclude them in the Product Backlog
- DBefore the release, they should be tested and validated in a hardening sprint
- ESpecific expectations can be used as acceptance criteria to specific product backlog items
- FImportant, recurring non-functional requirements can be added to the definition of done
How the community answered
(51 responses)- A75% (38)
- B16% (8)
- C4% (2)
- D6% (3)
Explanation
There is no hardening sprint, there are only regular sprints. If it's an ever recurring non-functional requirement, it can be added to the definition of done. If it's not it can be added (as a criteria) in the product backlog (item).