The increment must be released at the end of the sprint
The correct answer is B. False. It should be a working increment, but it's not mandatory to release it.
Developing Products
Question
The increment must be released at the end of the sprint
Options
- ATrue
- BFalse
How the community answered
(46 responses)- A7% (3)
- B93% (43)
Explanation
It should be a working increment, but it's not mandatory to release it.