PSD · Question #68
Who is responsible for the sizing / estimate of the product backlog?
The correct answer is C. Developers. The scrum guide says: "The Developers who will be doing the work are responsible for the sizing. The Product Owner may influence the Developers by helping them understand and select trade-
Applying Scrum
Question
Who is responsible for the sizing / estimate of the product backlog?
Options
- AScrum team
- BThe product owner
- CDevelopers
- DThe scrum master lets them know whether they need to be preset
How the community answered
(41 responses)- A2% (1)
- B2% (1)
- C88% (36)
- D7% (3)
Explanation
The scrum guide says: "The Developers who will be doing the work are responsible for the sizing. The Product Owner may influence the Developers by helping them understand and select trade-
Topics
#estimation#product backlog sizing#developers#sprint planning