PSD · Question #62

PSD Question #62: Real Exam Question with Answer & Explanation

The correct answer is D. All of these. All the scrum events are timeboxed.

Question

What event is timeboxed?

Options

  • ADaily Scrum
  • BSprint
  • CSprint planning
  • DAll of these
  • ESprint review
  • FSprint retrospective

Explanation

All the scrum events are timeboxed.