Scrum
PSD · Question #21
True or False: An Increment must be released to customers or users at the end of each Sprint.
The correct answer is B. False. While each Increment must meet the Definition of Done and be potentially releasable, releasing it is not mandatory. The decision to release lies with the Product Owner and stakeholders.
Applying Scrum
Question
True or False: An Increment must be released to customers or users at the end of each Sprint.
Options
- ATrue
- BFalse
How the community answered
(59 responses)- A7% (4)
- B93% (55)
Explanation
While each Increment must meet the Definition of Done and be potentially releasable, releasing it is not mandatory. The decision to release lies with the Product Owner and stakeholders.
Topics
#Sprint Increment#release decisions#Scrum artifacts