Scrum
PSD · Question #20
Which best describes the Product Backlog? (choose the best answer)
The correct answer is A. It is allowed to grow and change as more is learned about the product and its customers.. The Product Backlog is a dynamic artifact that evolves as the Scrum Team learns more about customer needs and product requirements. It reflects Scrum's empirical nature.
Applying Scrum
Question
Which best describes the Product Backlog? (choose the best answer)
Options
- AIt is allowed to grow and change as more is learned about the product and its customers.
- BIt provides just enough information to enable a Scrum Team to start the design phase of a product.
- CIt is baselined to follow change management processes.
- DIt contains all foreseeable tasks and requirements from which the Scrum Team can develop and
How the community answered
(40 responses)- A90% (36)
- B3% (1)
- D8% (3)
Explanation
The Product Backlog is a dynamic artifact that evolves as the Scrum Team learns more about customer needs and product requirements. It reflects Scrum's empirical nature.
Topics
#Product Backlog#emergent backlog#product discovery#backlog evolution