Question
Which concept is described by the Last Responsible Moment? (choose the best answer)
Options
- ADiscover decisions to be made as soon as possible but postpone making those decisions until the
- BMaking decisions as soon as possible to close feedback loops as soon as possible.
- CThe last moment in a Sprint when code changes are allowed; after this, only stabilization work
- DThe last moment a Developer is responsible for quality; after this, the Tester is responsible.