PMI-SP · Question #254
Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure: Management is reviewing the network diagram, and they are…
The correct answer is B. Day 22. Activity I must finish by Day 22, so that Activity J can start by Day 23. If Activity I finishes later than Day 22, the project will be late. Answer option D is incorrect. Day 19 is the earliest Activity I can finish. Answer option A is incorrect. Day 20 is the latest Activity…
Question
Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure:
Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?
Exhibit
Options
- ADay 20
- BDay 22
- CDay 17
- DDay 19
How the community answered
(42 responses)- A31% (13)
- B43% (18)
- C19% (8)
- D7% (3)
Explanation
Activity I must finish by Day 22, so that Activity J can start by Day 23. If Activity I finishes later than Day 22, the project will be late. Answer option D is incorrect. Day 19 is the earliest Activity I can finish. Answer option A is incorrect. Day 20 is the latest Activity I can start. Answer option C is incorrect. Day 17 is the earliest Activity I can start.
Topics
Community Discussion
No community discussion yet for this question.
