nerdexam
PMI

PMI-SP · Question #254

PMI-SP Question #254: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #254. The question stem and answer options stay visible for context.

Question

Jeff is the project manager of the GHY Project for his organization. He has created the project network diagram as shown in the figure: Management is reviewing the network diagram, and they are concerned about the latest date that Activity I can finish. What is the latest day Activity I can finish without affecting the project end date?

Exhibit

PMI-SP question #254 exhibit

Options

  • ADay 20
  • BDay 22
  • CDay 17
  • DDay 19

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice