PMI
PMI-SP · Question #253
PMI-SP Question #253: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #253. The question stem and answer options stay visible for context.
Question
You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your schedule variance for this project?
Options
- A$11,667
- B1.02
- C$7,000
- D$-111,750
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.