nerdexam
PMI

PMI-SP · Question #252

You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should…

The correct answer is B. $787,504. The project will need $787,504 more to complete. This formula, the estimate to complete, is estimate at completion minus the actual costs. Here, CPI = EV/AC =(0.40*1,258,456)/525000= 0.95882, and = (BAC/CPI) - AC =(1,258,456/0.95882) - 525000 = 1,312,504- 525000 The estimate to…

Schedule Monitoring and Controlling

Question

You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?

Options

  • A$566,305
  • B$787,504
  • C$1,312,504
  • D$733,456

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    46% (11)
  • C
    17% (4)
  • D
    29% (7)

Explanation

The project will need $787,504 more to complete. This formula, the estimate to complete, is estimate at completion minus the actual costs. Here, CPI = EV/AC =(0.40*1,258,456)/525000= 0.95882, and = (BAC/CPI) - AC =(1,258,456/0.95882) - 525000 = 1,312,504- 525000 The estimate to complete (ETC) is the expected cost needed to complete all the remaining work for a scheduled activity, a group of activities, or the project. ETC helps project managers predict what the final cost of the project will be upon completion. The formula for the ETC is EAC- AC. The EAC is BAC/CPI. Answer option C is incorrect. This is the estimate at completion. Answer option A is incorrect. This is the planned value. Answer option D is incorrect. This is not a valid value based on the current project performance.

Topics

#ETC#EVM#cost performance index#budget forecasting

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice