nerdexam
PMI

PMI-SP · Question #251

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart: What will…

The correct answer is C. 29. A three-point estimate records the optimistic, most likely, and the pessimistic duration and then records an average for the predicted duration. Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program…

Schedule Planning and Development

Question

Della works as a project manager for BlueWell Inc. She has asked her assistant Beth to provide activity duration estimate for an activity. Beth provides Della the following estimate chart:

What will be the activity duration according to the PERT three-point analysis?

Options

  • A19
  • B24
  • C29
  • D46

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    8% (4)
  • C
    71% (36)
  • D
    18% (9)

Explanation

A three-point estimate records the optimistic, most likely, and the pessimistic duration and then records an average for the predicted duration. Three-point estimate is a way to enhance the accuracy of activity duration estimates. This concept is originated with the Program Evaluation and Review Technique (PERT). PERT charts the following three estimates: Most likely (TM): The duration of activity based on realistic factors such as resources assigned, interruptions, etc. Optimistic (TO): The activity duration based on the best-case scenario Pessimistic (TP): The activity duration based on the worst-case scenario The expected (TE) activity duration is a weighted average of these three estimates: TE = (TO + 4TM + TP) / 6 Duration estimates based on the above equations (sometimes simple average of the three estimates is also used) provide TE = ( 24 + 28*4 + 36) / 6 Answer options B, D, and A are incorrect. These are not the valid answers for this question.

Topics

#PERT#three-point estimate#activity duration#schedule estimation

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice