The correct answer is C. Risk register. The project risks are documented in the risk register - including the probability and impact information. The risk register is an output of the Identify Risks process. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analys
Question
Options
- ARisk management plan
- BSchedule management plan
- CRisk register
- DActivity attributes
Explanation
The project risks are documented in the risk register - including the probability and impact information. The risk register is an output of the Identify Risks process. Risk register is a document that contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning. Description, category, cause, probability of occurring, impact on objectives, proposed responses, owner, and the current status of all identified risks are put in the Answer option A is incorrect. The risk management plan addresses that how risks will be identified, monitored, and controlled. Answer option D is incorrect. The activity attributes information is needed, but risks are not part of the activity attributes. Answer option B is incorrect. The schedule management plan addresses how the schedule will be created, executed, and controlled.
Community Discussion
No community discussion yet for this question.