nerdexam
PMI

PMI-SP · Question #248

You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for…

The correct answer is D. Change requests. Change requests are an output of performance report, and allow the project manager to address corrective actions and preventive actions to help the project get back in alignment with performance baselines. Answer option B is incorrect. While performance reports are an output of…

Schedule Monitoring and Controlling

Question

You are the project manager of the MQQ project. Unfortunately, this project is not performing well and you must do something to address the problems in your project. Based on your planning for monitoring and controlling project performance, you know that there are three outputs of performance reporting. Which one of the following is the only output that is most appropriate for this poorly performing project?

Options

  • AOrganizational process assets update
  • BPerformance reports
  • CPerformance re-baselining
  • DChange requests

How the community answered

(27 responses)
  • A
    7% (2)
  • B
    11% (3)
  • C
    4% (1)
  • D
    78% (21)

Explanation

Change requests are an output of performance report, and allow the project manager to address corrective actions and preventive actions to help the project get back in alignment with performance baselines. Answer option B is incorrect. While performance reports are an output of the performance reporting, these reports do not specifically address the problems in the project. Answer option A is incorrect. Updating the organizational process assets is an important activity, but it does not address the poor performance directly. Answer option C is incorrect. Performance re-baselining is not an output of performance reporting so this choice is not valid.

Topics

#performance reporting#change requests#process outputs#monitoring and controlling

Community Discussion

No community discussion yet for this question.

Full PMI-SP Practice