PMI-SP · Question #249
Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary…
The correct answer is A. Code of accounts. The code of accounts is a hierarchical numbering system that uniquely identifies each deliverable of the WBS and segments the WBS by levels of numbering. Answer option C is incorrect. Component numbering is not a valid term for project management. Answer option B is incorrect…
Question
Gary is the project manager of the NGH project for his organization. He and the project team have created the initial WBS. Before Gary and the project team begin creating the activity list, Gary wants the project team to help him create a unique numbering system for the deliverables identified in the WBS. What numbering system can Gary and the project team apply to the WBS to identify the components of the WBS?
Options
- ACode of accounts
- BChart of accounts
- CComponent numbering
- DActivity linkage sequencing
How the community answered
(26 responses)- A92% (24)
- C4% (1)
- D4% (1)
Explanation
The code of accounts is a hierarchical numbering system that uniquely identifies each deliverable of the WBS and segments the WBS by levels of numbering. Answer option C is incorrect. Component numbering is not a valid term for project management. Answer option B is incorrect. A chart of accounts is a financial tracking and assignment tool for common deliverables and activities an organization performs for its customers. Answer option D is incorrect. Activity linkage sequencing is not a valid project management term.
Topics
Community Discussion
No community discussion yet for this question.