Question

You are the project manager of the NHQ project. This project is slightly larger than the TR project, in which you also served as the project manager. You decide to use the actual activity duration of the GTR project as a basis for your current NHQ project. This, you reason, will save time for your project, as the previous project has provided the information. Which one of the following terms best describes the action you are doing in this scenario?

Options

  • AYou are creating an analogous estimate.
  • BYou are creating a bottom-up estimate.
  • CYou are relying on expert judgment.
  • DYou are creating a rough order of magnitude estimate.