PMI-SP · Question #228
You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft…
The correct answer is B. Scheduling tool. According to the PMBOK, automated scheduling tools expedite the scheduling process. The scheduling tool is used in combination with manual methods or further project management software to carry out the schedule network analysis to produce an updated project schedule. Answer…
Question
You are the project manager for your organization. You are working with your project team to develop the project schedule. You would like to automate much of the scheduling by using Microsoft project. Microsoft project as a scheduling tool is an example of what tool and technique for the Develop Schedule Process?
Options
- AOrganizational process asset
- BScheduling tool
- CProject Management Information System
- DProject office software
How the community answered
(48 responses)- A6% (3)
- B90% (43)
- C2% (1)
- D2% (1)
Explanation
According to the PMBOK, automated scheduling tools expedite the scheduling process. The scheduling tool is used in combination with manual methods or further project management software to carry out the schedule network analysis to produce an updated project schedule. Answer option C is incorrect. The project management information system is the complete project management software package beyond just the scheduling portion. Answer option D is incorrect. This is not a valid answer. Answer option A is incorrect. While the software may be made available as a part of organizational process assets, the best answer is the scheduling tool.
Topics
Community Discussion
No community discussion yet for this question.