PMI-SP · Question #227
You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is…
The correct answer is A. Schedule data. Schedule data is not an input to the control schedule process. Organizational process assets are the final input to the control schedule process. The inputs of schedule control process are as follows: Project Management Plan Project Schedule Work Performance Integration…
Question
You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?
Options
- ASchedule data
- BWork performance information
- CProject management plan
- DProject schedule
How the community answered
(59 responses)- A86% (51)
- B7% (4)
- C2% (1)
- D5% (3)
Explanation
Schedule data is not an input to the control schedule process. Organizational process assets are the final input to the control schedule process. The inputs of schedule control process are as follows: Project Management Plan Project Schedule Work Performance Integration Organizational Process Assets Answer option C is incorrect. The project management plan is an input to the control schedule Answer option D is incorrect. The project schedule is an input to the control schedule process. Answer option B is incorrect. Work performance information is an input to the control schedule