nerdexam
PMI

PMI-SP · Question #229

PMI-SP Question #229: Real Exam Question with Answer & Explanation

Sign in or unlock PMI-SP to reveal the answer and full explanation for question #229. The question stem and answer options stay visible for context.

Question

You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization. How much float can you use on Activity G if Activity B actually takes eight days to complete?

Exhibit

PMI-SP question #229 exhibit

Options

  • AFour
  • BThree
  • CSeven
  • DZero

Unlock PMI-SP to see the answer

You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PMI-SP Practice