PMI
PMI-SP · Question #229
PMI-SP Question #229: Real Exam Question with Answer & Explanation
Sign in or unlock PMI-SP to reveal the answer and full explanation for question #229. The question stem and answer options stay visible for context.
Question
You are the project manager for the NGH project. The figure given below represents the small project you are completing for your organization. How much float can you use on Activity G if Activity B actually takes eight days to complete?
Exhibit
Options
- AFour
- BThree
- CSeven
- DZero
Unlock PMI-SP to see the answer
You've previewed enough free PMI-SP questions. Unlock PMI-SP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
