PMI-SP · Question #162
Which of the following are inputs to Activity Definition?
The correct answer is A. Project Scope Statement and Work Breakdown Structure. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
Which of the following are inputs to Activity Definition?
Options
- AProject Scope Statement and Work Breakdown Structure
- BActivity list and Arrow Diagram
- CChange Requests Lists and Organizational Process Assets
- DProject Management Plan and Resource Availability
How the community answered
(36 responses)- A89% (32)
- B3% (1)
- C3% (1)
- D6% (2)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#activity definition#scope statement#WBS inputs#schedule planning