Which of the following are inputs to Activity Definition?

The correct answer is A. Project Scope Statement and Work Breakdown Structure. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

Which of the following are inputs to Activity Definition?

Options

  • AProject Scope Statement and Work Breakdown Structure
  • BActivity list and Arrow Diagram
  • CChange Requests Lists and Organizational Process Assets
  • DProject Management Plan and Resource Availability

How the community answered

(36 responses)
  • A
    89% (32)
  • B
    3% (1)
  • C
    3% (1)
  • D
    6% (2)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#activity definition#scope statement#WBS inputs#schedule planning