Which of the following inputs is required for the WBS creation?
The correct answer is D. Project Scope Management Plan. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
Which of the following inputs is required for the WBS creation?
Options
- AProject Quality Plan
- BProject Schedule Network
- CProject Management Software
- DProject Scope Management Plan
How the community answered
(27 responses)- A4% (1)
- C7% (2)
- D89% (24)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#WBS creation#scope management plan#work breakdown structure#planning inputs