While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

The correct answer is A. Utilize the change control process. You've hit your limit · resets 5am (America/New_York)

Schedule Monitoring and Controlling

Question

While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?

Options

  • AUtilize the change control process.
  • BCrash the schedule to fix the defect.
  • CLeave the defect in and work around it.
  • DFast-track the remaining development.

How the community answered

(29 responses)
  • A
    72% (21)
  • B
    3% (1)
  • C
    7% (2)
  • D
    17% (5)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#change control process#defect management#integrated change control#schedule impact