Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?
The correct answer is D. Activity Resource Estimating. You've hit your limit · resets 5am (America/New_York)
Schedule Planning and Development
Question
Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?
Options
- ASchedule Control
- BActivity Definition
- CSchedule Development
- DActivity Resource Estimating
How the community answered
(45 responses)- A2% (1)
- B2% (1)
- C9% (4)
- D87% (39)
Explanation
You've hit your limit · resets 5am (America/New_York)
Topics
#activity resource estimating#resource breakdown structure#resource requirements#schedule outputs