PMI-SP · Question #163

Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

The correct answer is D. Activity Resource Estimating. You've hit your limit · resets 5am (America/New_York)

Schedule Planning and Development

Question

Activity resource requirements and resource breakdown structure are outputs from what Project Time Management process?

Options

  • ASchedule Control
  • BActivity Definition
  • CSchedule Development
  • DActivity Resource Estimating

How the community answered

(45 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    9% (4)
  • D
    87% (39)

Explanation

You've hit your limit · resets 5am (America/New_York)

Topics

#activity resource estimating#resource breakdown structure#resource requirements#schedule outputs