PMIPMI
PMI-RMP · Question #92
PMI-RMP Question #92: Real Exam Question with Answer & Explanation
The correct answer is C: Fallback plan. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?
Options
- AMitigation management plan
- BMitigation plan
- CFallback plan
- DRisk response plan
Topics
#Risk response planning#Fallback plan#Contingency planning#Risk response failure
Community Discussion
No community discussion yet for this question.