nerdexam
PMIPMI

PMI-RMP · Question #92

PMI-RMP Question #92: Real Exam Question with Answer & Explanation

The correct answer is C: Fallback plan. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?

Options

  • AMitigation management plan
  • BMitigation plan
  • CFallback plan
  • DRisk response plan

Topics

#Risk response planning#Fallback plan#Contingency planning#Risk response failure

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions