PMI-RMP · Question #92
You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation…
The correct answer is C. Fallback plan. A Fallback Plan is the correct answer. A fallback plan is developed and used when the primary risk response strategy is not effective or is insufficient to address the risk. It is essentially a 'Plan B' that is triggered when the originally selected risk strategy fails to…
Question
You work as a project manager for SoftTech Inc. You have implemented the risk action plan and it was not effective. What type of plan should you as a project manager will create for implementation if a selected risk strategy fails to be fully effective?
Options
- AMitigation management plan
- BMitigation plan
- CFallback plan
- DRisk response plan
How the community answered
(67 responses)- A1% (1)
- B4% (3)
- C93% (62)
- D1% (1)
Explanation
A Fallback Plan is the correct answer. A fallback plan is developed and used when the primary risk response strategy is not effective or is insufficient to address the risk. It is essentially a 'Plan B' that is triggered when the originally selected risk strategy fails to adequately manage the risk. This is different from a Risk Response Plan (D), which is the broader document containing all planned risk responses. A Mitigation Plan (B) specifically aims to reduce the probability or impact of a risk - it is a type of response, not a backup. A 'Mitigation Management Plan' (A) is not a standard PMI-recognized term. The fallback plan is pre-planned so the team is prepared to act quickly if the primary response proves inadequate.
Topics
Community Discussion
No community discussion yet for this question.