nerdexam
PMIPMI

PMI-RMP · Question #91

PMI-RMP Question #91: Real Exam Question with Answer & Explanation

The correct answer is A: Transference. See the full explanation below for the reasoning.

Risk Strategy and Planning

Question

Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?

Options

  • ATransference
  • BAvoidance
  • CContractual
  • DMitigation

Topics

#Risk Response Strategies#Transference#Risk Planning

Community Discussion

No community discussion yet for this question.

Full PMI-RMP PracticeBrowse All PMI-RMP Questions