PMIPMI
PMI-RMP · Question #91
PMI-RMP Question #91: Real Exam Question with Answer & Explanation
The correct answer is A: Transference. See the full explanation below for the reasoning.
Risk Strategy and Planning
Question
Linda is the project manager of the NAB Project. One of the risks her project team has identified is too dangerous for the project team to manage internally so she has hired a vendor to complete this portion of the project and to manage the identified risk. What risk response has Linda used in this instance?
Options
- ATransference
- BAvoidance
- CContractual
- DMitigation
Topics
#Risk Response Strategies#Transference#Risk Planning
Community Discussion
No community discussion yet for this question.